710 El Camino Del Mar #0
San Francisco permit 202410243675 · Seacliff
Renovation of interior spaces; replacement of the (e) stairs, reconfiguration of some windows on the east facade, and a comprehensive transformation of the rear (north) facade to incorporate new windows, new finishes, and fixtures throughout.
- Filed
- Nov 19, 2024
- Issued
- Feb 12, 2025 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 24, 2024 | Oct 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 24, 2024 | Oct 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 24, 2024 | Oct 24, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2024 | Oct 24, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 25, 2024 | Oct 25, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Oct 30, 2024 | Nov 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 30, 2024 | Oct 30, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 5, 2024 | Nov 5, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 8, 2024 | Nov 8, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 14, 2024 | Nov 14, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 19, 2024 | Nov 19, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2024 | Nov 20, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 20, 2024 | Jan 21, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 20, 2024 | Nov 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2024 | Dec 13, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2024 | Dec 2, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 20, 2024 | Feb 7, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 22, 2025 | Jan 22, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Jan 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 3, 2025 | Feb 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2025 | Feb 4, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 4, 2025 | Feb 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2025 | Feb 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 5, 2025 | Feb 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2025 | Feb 12, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,000,000
| Name | Role | License on permit |
|---|---|---|
| Glenda Flaim | Architect | C-32433 |
| Adam Frederick Klein Bkg Structural Engineers | Engineer | S5941 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2026