209 Henry St
San Francisco permit 202410253744 · Castro/Upper Market
Interior remodel w/2 story rear horizontal addition exempt from 311 pursuant to sec.311.b.3. convert 1183sf of (e) garage space to conditioned living +1 garage car. (n)skylights. windows at rear and side. (n) radiant heating,water heater,electrical. excavate 20", 2new baths@1st fl
- Filed
- Nov 19, 2024
- Issued
- Apr 18, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 25, 2024 | Oct 25, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 25, 2024 | Oct 25, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2024 | Oct 25, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 25, 2024 | Oct 25, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Oct 25, 2024 | Oct 25, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Oct 31, 2024 | Nov 15, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 8, 2024 | Nov 8, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 15, 2024 | Nov 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2024 | Nov 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 19, 2024 | Jan 23, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2024 | Nov 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 19, 2024 | Nov 26, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 19, 2024 | Apr 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 13, 2025 | Mar 10, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 12, 2025 | Mar 20, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 25, 2025 | Mar 25, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 27, 2025 | Mar 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 27, 2025 | Mar 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 27, 2025 | Apr 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2025 | Mar 31, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2025 | Apr 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 8, 2025 | Apr 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $848,440
| Name | Role | License on permit |
|---|---|---|
| Stephen G Verner | Architect | C-34368 |
| Donald David Double D Engineering | Engineer | S-3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025