Interior remodel w/2 story rear horizontal addition exempt from 311 pursuant to sec.311.b.3. convert 1183sf of (e) garage space to conditioned living +1 garage car. (n)skylights. windows at rear and side. (n) radiant heating,water heater,electrical. excavate 20", 2new baths@1st fl

Timeline
Key dates from the city record.
Filed
Nov 19, 2024
Issued
Apr 18, 2025 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 6 departments
Comments issued
Twice, by Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Oct 25, 2024Administrative

Zoning review

Planning · CP-ZOC

Oct 25, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 25, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Oct 25, 2024Not Applicable

Fire prevention review

Fire Department · SFFD

Oct 25, 2024Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Nov 15, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Nov 8, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Nov 15, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 19, 2024Administrative

Building plan review

Building Inspection · BLDG

Jan 23, 2025Administrative

Street use and mapping

Public Works · DPW-BSM

Nov 21, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 26, 2024Approved

Permit Processing Center

Building Inspection · PPC

Apr 8, 2025Administrative

Building plan review

Building Inspection · BLDG

Mar 10, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 20, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 25, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 28, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Apr 4, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 31, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Apr 7, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Apr 18, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$848,440
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Stephen G VernerArchitectC-34368
Donald David

Double D Engineering

EngineerS-3928
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202410253744 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record