1735 47th Av
San Francisco permit 202410283881 · Sunset/Parkside
New horizontal addition @ rear yard. new vertical 3rd floor addition & decks. new exterior cladding throughout. modifications to front facade. reconfiguration of interior walls. new interior stairs, relocate interior bathrooms & kitchen.
- Filed
- Nov 13, 2024
- Issued
- May 2, 2025 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 23, 2024 | Nov 8, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 28, 2024 | Oct 28, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2024 | Nov 14, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 1, 2024 | Nov 1, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 5, 2024 | Nov 5, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 8, 2024 | Nov 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 14, 2024 | Nov 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 14, 2024 | Jan 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2024 | Dec 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 14, 2024 | Nov 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2024 | Nov 21, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 14, 2024 | Apr 22, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2025 | Jan 21, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2025 | Feb 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2025 | Feb 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2025 | Feb 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 7, 2025 | Feb 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 26, 2025 | Feb 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2025 | Feb 27, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 3, 2025 | Mar 3, 2025 | Administrative |
Development fee collection Building Inspection · DFCU | Mar 3, 2025 | Mar 5, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2025 | May 2, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Mar 13, 2025 | Mar 20, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 16, 2025 | Apr 16, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Zachary Benjamin Meade Pristereo | Architect | C36088 |
| Alexander Michael Santos Altos Engineering | Engineer | C84144 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021