252 Cumberland St
San Francisco permit 202410283893 · Castro/Upper Market
Permit to comply with planning enforcement notice 2021-005279. changes to ground floor to establish second unit including (n)1 hour wall, (n) 20 minute doors (n) kitchen remodel, conversion of former wine storage to (n) bedroom addition of trellis above entry at front facade, addition of parapet
- Filed
- Oct 28, 2024
- Issued
- Dec 18, 2024 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 9 stops across 3 departments
- Comments issued
- Twice, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 28, 2024 | Oct 28, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 29, 2024 | Oct 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 1, 2024 | Nov 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2024 | Nov 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2024 | Dec 4, 2024 | Approved |
Intake Building Inspection · INTAKE | Dec 11, 2024 | Dec 11, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 11, 2024 | Dec 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | Dec 18, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $201,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Ross Levine Andy Levine Architect | Architect | C-14090 |
| Rod Massoudi Massoudi Consulting Engineer | Engineer | C-81412 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023