214 Spruce St
San Francisco permit 202410293938 · Presidio Heights
Full interior remodel and 1684 sf addition, including various exterior improvements and mep upgrades throughout the area of work.
- Filed
- Jan 3, 2025
- Issued
- Jun 10, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 22, 2024 | Nov 8, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 1, 2024 | Nov 1, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 1, 2024 | Nov 1, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Nov 8, 2024 | Nov 8, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 18, 2024 | Dec 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 25, 2024 | Nov 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 11, 2024 | Dec 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 11, 2024 | Jan 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 6, 2025 | Jan 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Feb 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 6, 2025 | Jan 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 6, 2025 | Jan 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2025 | Jan 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2025 | Jan 13, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 6, 2025 | May 29, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2025 | Mar 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 17, 2025 | Apr 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 18, 2025 | Apr 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 5, 2025 | May 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 5, 2025 | May 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2025 | May 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2025 | May 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 20, 2025 | May 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 20, 2025 | May 28, 2025 | Approved |
Development fee collection Building Inspection · DFCU | May 28, 2025 | May 28, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 29, 2025 | Jun 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,000,000
| Name | Role | License on permit |
|---|---|---|
| Richard Doyle Beard Richard Beard | Architect | C12947 |
| David M Strandberg Strandberg Engineering | Engineer | 62993 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026