600 20th St
San Francisco permit 202410294000 · Potrero Hill
Construction of drill displacement column (ddc)ground improvement system & excavation to bottom of proposed concrete foundation elevations. the pa# for replacement building is #202110019676. ref demo pa# 202407227013.
- Filed
- Nov 27, 2024
- Issued
- Mar 25, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Public Works, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 25, 2024 | Nov 8, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 31, 2024 | Oct 31, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 1, 2024 | Nov 1, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 5, 2024 | Nov 5, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Nov 12, 2024 | Nov 21, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 19, 2024 | Nov 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 22, 2024 | Nov 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 27, 2024 | Dec 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 27, 2024 | Jan 24, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2024 | Nov 27, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Nov 27, 2024 | Dec 2, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 27, 2024 | Mar 4, 2025 | Administrative |
Public Health HEALTH-MH | Dec 2, 2024 | Dec 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2025 | Feb 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2025 | Feb 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2025 | Feb 12, 2025 | Approved |
Public Health HEALTH-MH | Feb 11, 2025 | Feb 11, 2025 | Issued Comments |
Public Health HEALTH-MH | Mar 4, 2025 | Mar 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2025 | Mar 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Michael Howard Pitler Workshop1 | Architect | C-30445 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026