1101 Fillmore St
San Francisco permit 202410314105 · Western Addition
Modifications to existing att facility: r/r 5 antennas, add one new air antenna; remove 9 rrus, install 8 plus 2 mounts; remove 3 diplexer; install one 6648 bbu; 1 new fif rack; install 58v retrofit kit (neq 53008) in existing dcpp; install new rf safety signs, barricades + stripping at rooftop.
- Filed
- Oct 31, 2024
- Issued
- Feb 26, 2025 (4 months after filing)
- Completed
- Jul 17, 2025 (5 months after issuance)
- Review stops
- 10 stops across 4 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Oct 31, 2024 | Oct 31, 2024 | Administrative |
Intake Building Inspection · INTAKE | Oct 31, 2024 | Oct 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 31, 2024 | Oct 31, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 31, 2024 | Oct 31, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2024 | Oct 31, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 31, 2024 | Oct 31, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 31, 2024 | Oct 31, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 31, 2024 | Oct 31, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 31, 2024 | Oct 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2025 | Feb 26, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $65,000
| Name | Role | License on permit |
|---|---|---|
| Seung Kun Oh | Engineer | S6836 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026