Rear yard remodel includes: existing deck and concrete patio to be removed, new retaining wall, new wood deck, new concrete stair and landing to lower yard area, new hot tub to be installed on wood deck.
- Filed
- Dec 2, 2024
- Issued
- Jul 7, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 4 times, by Public Utilities, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 31, 2024 | Oct 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 31, 2024 | Oct 31, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 31, 2024 | Oct 31, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Nov 7, 2024 | Dec 2, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 2, 2024 | Dec 3, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 3, 2024 | Dec 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 3, 2024 | Jan 24, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 3, 2024 | Jun 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2025 | Mar 28, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2025 | Feb 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2025 | Mar 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 18, 2025 | Apr 29, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 14, 2025 | May 23, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | May 23, 2025 | May 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 23, 2025 | May 23, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 23, 2025 | May 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2025 | May 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 23, 2025 | Jun 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2025 | Jul 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $185,000
| Name | Role | License on permit |
|---|---|---|
| Karen Mar Marjang Design | Architect | C25227 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2014