304 Shotwell St
San Francisco permit 202411044296 · Mission
Int renov of(e)2 stry comm bldg. no chg of occy. scope inc (n)b-rms, k-nette & stu spc. create n int ct.yd at rear w/sld dr sys by rmv 15' of rear rf, n int stwy & mezz. occy w/not inc pub accom. demo u/pa202410152923
- Filed
- Jan 30, 2025
- Issued
- Jun 2, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 4, 2024 | Nov 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 4, 2024 | Nov 4, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 4, 2024 | Nov 20, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2024 | Nov 13, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 15, 2024 | Nov 15, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 15, 2024 | Nov 15, 2024 | — |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 18, 2024 | Nov 18, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 15, 2025 | Jan 28, 2025 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 27, 2025 | Jan 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2025 | Jan 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 30, 2025 | Jan 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2025 | Feb 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 30, 2025 | Feb 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2025 | Mar 13, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 30, 2025 | Feb 11, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2025 | Feb 5, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 30, 2025 | May 23, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 28, 2025 | May 1, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 28, 2025 | May 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 13, 2025 | May 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 15, 2025 | May 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2025 | May 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 19, 2025 | May 21, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 19, 2025 | May 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2025 | May 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 23, 2025 | Jun 2, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $922,975
| Name | Role | License on permit |
|---|---|---|
| James William Zack Zack/Devito Architecture | Architect | C24446 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022