3001 Pacific Av #0
San Francisco permit 202411054395 · Pacific Heights
Interior remodel(e)5-story sfr w/10-bedrooms, 6-full baths and 8-half baths w/new roof terrace @(e)roof lvl, horizontal addition of new single story w/roof terrace. interior remodel to(e) 1-story detached garage to include new interior pool. new count to be 7-bedrooms, 8-full baths and 4-half baths.
- Filed
- Apr 22, 2025
- Issued
- Apr 10, 2026 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 43 stops across 7 departments
- Comments issued
- 17 times, by Permit Center, Building Inspection, Public Works, Public Utilities, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 1, 2024 | Nov 20, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Nov 5, 2024 | Apr 23, 2025 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 6, 2024 | Nov 6, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 18, 2024 | Nov 18, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 19, 2024 | Nov 19, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 30, 2024 | Jan 14, 2025 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jan 9, 2025 | Jan 9, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 6, 2025 | Feb 24, 2025 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Feb 19, 2025 | Feb 19, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 3, 2025 | Apr 18, 2025 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 17, 2025 | Apr 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 23, 2025 | Apr 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | May 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2025 | Jun 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 23, 2025 | May 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2025 | May 1, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 23, 2025 | Jun 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2025 | Apr 29, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Apr 23, 2025 | Apr 23, 2025 | Administrative |
Public Health HEALTH-MH | Apr 23, 2025 | Apr 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 23, 2025 | Feb 18, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 28, 2025 | May 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 28, 2025 | May 28, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | May 28, 2025 | May 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 10, 2025 | Aug 4, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 10, 2025 | Nov 24, 2025 | Issued Comments |
Public Health HEALTH-MH | Nov 13, 2025 | Nov 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 17, 2025 | Nov 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 17, 2025 | Nov 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 18, 2025 | Nov 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2025 | Nov 19, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 24, 2025 | Nov 24, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 17, 2025 | Dec 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 26, 2025 | Dec 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 30, 2025 | Dec 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 30, 2025 | Dec 30, 2025 | Approved |
Public Health HEALTH-MH | Jan 9, 2026 | Jan 9, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 2, 2026 | Feb 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2026 | Feb 6, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2026 | Feb 2, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Feb 2, 2026 | Feb 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2026 | Feb 5, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 18, 2026 | Apr 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $4,315,170
| Name | Role | License on permit |
|---|---|---|
| Geoffrey Gibson Winder Gison Architects | Architect | C35924 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020