Per ab1114:(e) 1st fl space is proposed to be deemed an adu via governmental code section 65852-2(a)-(d)ord 95-17.(n)rear(e)deck & stair.(n)interior remodeling of(e)space,upgrading(e)bath,(n)kitchen cabinets & appliances.(n)hvac& lighting.(n)wall to separate laundry space from garage.
- Filed
- Nov 26, 2024
- Issued
- Apr 14, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 30 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 1, 2024 | Nov 21, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 6, 2024 | Nov 6, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2024 | Nov 13, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 18, 2024 | Nov 18, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 21, 2024 | Nov 21, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 21, 2024 | Nov 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 25, 2024 | Nov 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 26, 2024 | Dec 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 26, 2024 | Dec 3, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 26, 2024 | Dec 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 26, 2024 | Dec 3, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 26, 2024 | Dec 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 26, 2024 | Nov 27, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 26, 2024 | Nov 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 26, 2024 | Dec 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 26, 2024 | Mar 20, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 9, 2024 | Dec 9, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 21, 2025 | Jan 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 23, 2025 | Jan 24, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 27, 2025 | Jan 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2025 | Feb 25, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 11, 2025 | Mar 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 12, 2025 | Mar 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2025 | Mar 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 12, 2025 | Mar 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2025 | Mar 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2025 | Mar 14, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Mar 20, 2025 | Mar 20, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2025 | Apr 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $65,300
| Name | Role | License on permit |
|---|---|---|
| Terryl Marshall Lofrano Lofrano Architecture | Architect | C7292 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022