San Francisco permit 202411054420 · Inner Sunset

ADUFull plan reviewExpired
Street view · Apr 2022
Google Street View of 1235 08th Av, Apr 2022
Scope of work
As written on the permit application.

Per ab1114:(e) 1st fl space is proposed to be deemed an adu via governmental code section 65852-2(a)-(d)ord 95-17.(n)rear(e)deck & stair.(n)interior remodeling of(e)space,upgrading(e)bath,(n)kitchen cabinets & appliances.(n)hvac& lighting.(n)wall to separate laundry space from garage.

Timeline
Key dates from the city record.
Filed
Nov 26, 2024
Issued
Apr 14, 2025 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 6 departments
Comments issued
9 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Nov 21, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Nov 6, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Nov 13, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Nov 18, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Nov 21, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Nov 21, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 26, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 5, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 3, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 6, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 3, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 10, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 27, 2024Approved

Urban forestry

Public Works · DPW-BUF

Nov 26, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 3, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 20, 2025Administrative

Building plan review

Building Inspection · BLDG

Dec 9, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 23, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 24, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 27, 2025Approved

Building plan review

Building Inspection · BLDG

Feb 6, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 25, 2025Approved

Urban forestry

Public Works · DPW-BUF

Mar 11, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 19, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 14, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 12, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Mar 13, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 14, 2025Approved

Development fee collection

Building Inspection · DFCU

Mar 20, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 14, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Expired
Estimated cost
$65,300
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Terryl Marshall Lofrano

Lofrano Architecture

ArchitectC7292
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202411054420 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record