2937 24th St
San Francisco permit 202411054426 · Mission
Renovation of (e) bakery/limited restaurant and new equipment, lighting, hvac plumving, electrical finishes, accessible lift and accessible restroom. no exterior changes. not a change of use.
- Filed
- Nov 5, 2024
- Issued
- Jun 5, 2025 (7 months after filing)
- Completed
- Jul 21, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Planning, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Nov 5, 2024 | Nov 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 5, 2024 | Nov 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 5, 2024 | Nov 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 10, 2024 | Dec 11, 2024 | Approved |
Intake Building Inspection · INTAKE | Dec 11, 2024 | Dec 11, 2024 | Administrative |
Public health review Public Health · HEALTH | Dec 11, 2024 | Dec 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 31, 2024 | Dec 31, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2025 | Jan 7, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 7, 2025 | Jan 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2025 | Feb 6, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 25, 2025 | Feb 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2025 | Mar 11, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 13, 2025 | Mar 13, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 13, 2025 | Mar 13, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 19, 2025 | Mar 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2025 | Apr 10, 2025 | Approved |
Public health review Public Health · HEALTH | Apr 10, 2025 | Apr 10, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Apr 10, 2025 | Apr 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 30, 2025 | May 30, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | May 30, 2025 | May 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2025 | Jun 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2025 | Jun 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2025 | Jun 5, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $345,798
| Name | Role | License on permit |
|---|---|---|
| Christopher James Sullivan Christopher J Sullivan | Architect | C-30234 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022