1208 Stanyan St
San Francisco permit 202411054454 · Haight Ashbury
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revison to permit 201811075321. as-built floor plans per inspector (michael chan)'s request.
- Filed
- Nov 5, 2024
- Issued
- Feb 21, 2025 (4 months after filing)
- Completed
- May 12, 2025 (3 months after issuance)
- Review stops
- 17 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 5, 2024 | Nov 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 5, 2024 | Nov 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2024 | Nov 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2024 | Nov 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2024 | Feb 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 29, 2025 | Jan 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2025 | Jan 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2025 | Jan 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2025 | Feb 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2025 | Feb 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2025 | Feb 12, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2025 | Feb 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2025 | Feb 12, 2025 | Not Applicable |
Intake Building Inspection · INTAKE | Feb 19, 2025 | Feb 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 19, 2025 | Feb 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 19, 2025 | Feb 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 21, 2025 | Feb 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| John Alan Goldman Kodorski | Architect | C14203 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026