2434 A 43rd Av
San Francisco permit 202411074555 · Sunset/Parkside
To erect 1 story, no basement, type v, detached adu at rear of house.
- Filed
- Nov 19, 2024
- Issued
- Nov 13, 2025 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 32 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 28, 2024 | Nov 15, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 8, 2024 | Nov 8, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2024 | Nov 13, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 13, 2024 | Nov 13, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2024 | Nov 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 21, 2024 | Nov 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Dec 19, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 21, 2024 | Dec 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2024 | Dec 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 21, 2024 | Nov 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2024 | Nov 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2024 | Dec 12, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 21, 2024 | Jun 16, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 28, 2025 | Jan 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 3, 2025 | Mar 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 3, 2025 | Mar 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 3, 2025 | Mar 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2025 | Mar 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 3, 2025 | Mar 5, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2025 | Mar 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2025 | Mar 4, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 18, 2025 | Apr 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 25, 2025 | Apr 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 14, 2025 | May 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 11, 2025 | Jun 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2025 | Jun 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2025 | Jun 13, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jun 16, 2025 | Jun 16, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2025 | Jun 25, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 13, 2025 | Nov 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $170,607
| Name | Role | License on permit |
|---|---|---|
| Jerome Douglas Tobias Arcflux Studio | Architect | C34070 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2026