1515 South Van Ness Av
San Francisco permit 202411074565 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Ed 13-01. priority prj - alter site to pa# 202306059259 s: construction type changed to 1-b from 1-a. early childhood education center occupancy type changed to 1-4 from e.revision from issued site permit present on g001,g400,g401,a300 & a302. all other sheets are indentical to approved site permit.
- Filed
- Nov 21, 2024
- Issued
- Jan 3, 2025 (1 month after filing)
- Completed
- Not completed yet
- Review stops
- 148 stops across 7 departments
- Comments issued
- 29 times, by Building Inspection, Public Works, Planning, Fire Department, Public Utilities
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 4, 2024 | Nov 19, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2024 | Nov 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2024 | Nov 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 21, 2024 | Nov 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Dec 4, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 21, 2024 | Dec 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2024 | Nov 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2024 | Nov 27, 2024 | Approved |
Public health review Public Health · HEALTH | Nov 21, 2024 | Nov 21, 2024 | Administrative |
Public Health HEALTH-MH | Nov 21, 2024 | Nov 26, 2024 | Approved |
Public Health HEALTH-AQ | Nov 21, 2024 | Dec 19, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 21, 2024 | Jan 2, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Dec 4, 2024 | Dec 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 17, 2024 | Dec 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 17, 2024 | Dec 17, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Dec 19, 2024 | Dec 19, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2024 | Dec 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 19, 2024 | Dec 20, 2024 | Approved |
Public Health HEALTH-MH | Dec 19, 2024 | Dec 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2024 | Dec 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 2, 2025 | Jan 3, 2025 | Administrative |
Addendum 1: Smp - dph
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 10, 2025 | Jan 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Jan 28, 2025 | Administrative |
Public health review Public Health · HEALTH | Jan 28, 2025 | Jan 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 28, 2025 | Jan 29, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 29, 2025 | Jan 31, 2025 | Administrative |
Addendum 2: Shoring excavation soils improvmeent rough grading
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 5, 2024 | Dec 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 31, 2024 | Jan 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Jan 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2025 | Jan 21, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Jan 6, 2025 | Jan 8, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 6, 2025 | Feb 11, 2025 | Administrative |
Public Health HEALTH-MH | Jan 8, 2025 | Jan 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2025 | Feb 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2025 | Feb 13, 2025 | Administrative |
Addendum 3: Foundation superstructure underground mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2025 | Feb 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2025 | Feb 7, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 7, 2025 | Feb 10, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 7, 2025 | Feb 7, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 7, 2025 | Feb 8, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2025 | Feb 10, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 7, 2025 | Feb 11, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2025 | Feb 13, 2025 | Administrative |
Addendum 4: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 25, 2025 | Mar 13, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Feb 26, 2025 | Mar 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 13, 2025 | Mar 28, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 13, 2025 | Mar 19, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 13, 2025 | May 28, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 13, 2025 | May 13, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 23, 2025 | May 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 23, 2025 | May 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 28, 2025 | Jun 2, 2025 | Administrative |
Addendum 5: Arch mep landscaping
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2025 | Feb 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2025 | Feb 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 14, 2025 | Feb 27, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 14, 2025 | Mar 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 14, 2025 | Feb 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 14, 2025 | Feb 20, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 14, 2025 | Feb 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2025 | Feb 20, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 14, 2025 | May 11, 2026 | Administrative |
Electrical plan review Building Inspection · MECH-E | Feb 24, 2025 | Feb 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 24, 2025 | Jul 1, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 24, 2025 | Jun 24, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 9, 2025 | Jul 11, 2025 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 21, 2025 | Oct 21, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 29, 2025 | Nov 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 29, 2025 | Oct 29, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 4, 2025 | Nov 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 5, 2025 | Nov 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 10, 2025 | Dec 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 10, 2025 | Dec 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2025 | Dec 15, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 11, 2026 | Feb 11, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 4, 2026 | Mar 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 17, 2026 | Apr 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 17, 2026 | May 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 17, 2026 | Apr 21, 2026 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 17, 2026 | Apr 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 17, 2026 | Apr 22, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 17, 2026 | Apr 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 17, 2026 | Apr 24, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2026 | Apr 21, 2026 | Approved |
Address verification Building Inspection · ADDR | May 5, 2026 | May 5, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 8, 2026 | May 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 11, 2026 | May 13, 2026 | Administrative |
Addendum 6: Fire sprinkler underground
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 26, 2025 | Apr 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2025 | Apr 11, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 14, 2025 | Apr 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2025 | May 8, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 14, 2025 | Sep 18, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jul 18, 2025 | Jul 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 12, 2025 | Sep 12, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2025 | Sep 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 18, 2025 | Sep 29, 2025 | Administrative |
Addendum 7: Fire sprinkler above ground
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 28, 2026 | Feb 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2026 | Feb 18, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 18, 2026 | Mar 12, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Feb 18, 2026 | Feb 19, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 18, 2026 | Jul 14, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Jul 14, 2026 | Jul 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2026 | Jul 23, 2026 | Administrative |
Addendum 8: Fire alarm & elevator 2-way com system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 8, 2026 | Jun 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2026 | Jun 12, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Jun 12, 2026 | Jun 29, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 12, 2026 | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | Sep 14, 2026 | Sep 23, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 9: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 12, 2025 | Dec 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 29, 2025 | Dec 29, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Dec 29, 2025 | Jan 20, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 29, 2025 | Mar 18, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Feb 24, 2026 | Mar 18, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2026 | Mar 24, 2026 | Administrative |
Addendum 10: Ebm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 27, 2026 | Sep 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2026 | Sep 16, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 17, 2026 | Oct 27, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 17, 2026 | Oct 19, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Sep 17, 2026 | Sep 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2026 | Sep 24, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 17, 2026 | Oct 27, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 27, 2026 | Nov 2, 2026 | Administrative |
Addendum 12: Solar pv/solar hot water
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 3, 2026 | Jun 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2026 | Jun 17, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 18, 2026 | Jul 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 18, 2026 | Jul 23, 2026 | Not Applicable |
Electrical plan review Building Inspection · MECH-E | Jun 18, 2026 | Jun 22, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 18, 2026 | Jul 22, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 18, 2026 | In progress | In Progress |
Building plan review quality control Building Inspection · BLDG-QC | Jul 27, 2026 | Jul 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 14: Steel stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 9, 2025 | Oct 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2025 | Oct 17, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 17, 2025 | Nov 13, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 17, 2025 | Nov 10, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Oct 17, 2025 | Nov 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2025 | Oct 23, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 17, 2025 | Dec 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 9, 2025 | Dec 10, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Dec 10, 2025 | Dec 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2025 | Dec 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 16, 2025 | Dec 23, 2025 | Administrative |
Addendum 15: Evacuation signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Caroline Joy Souza Caroline Souza | Architect | C35830 |
| David Joseph Rossi Kpff | Engineer | 4127 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026