1270 Valencia St
San Francisco permit 202411084703 · Mission
To comply w/ nov# 202305585 and planning #2023-002956enf, removing 5 (e) skylights, adding 21 skylights, add continuous dormers on the north/south sides of roof w/ clearstory windows. note (e) ridge to remain. make restrooms on 2/f accessible. remove non-permit cook, plumbing fixtures/appliances.
- Filed
- Feb 10, 2025
- Issued
- Feb 24, 2026 (12 months after filing)
- Completed
- Oct 28, 2026 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 13 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 7, 2024 | Nov 21, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 15, 2024 | Nov 15, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 19, 2024 | Nov 19, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 3, 2025 | Feb 10, 2025 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 6, 2025 | Feb 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2025 | Feb 11, 2025 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 10, 2025 | Feb 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 11, 2025 | Feb 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2025 | Mar 24, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2025 | Mar 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2025 | Mar 24, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 11, 2025 | Feb 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 11, 2025 | Mar 4, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2025 | Feb 19, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 11, 2025 | Feb 11, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Feb 11, 2025 | Feb 12, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Feb 11, 2025 | Feb 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 16, 2025 | Oct 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 16, 2025 | Oct 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2025 | Sep 19, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 16, 2025 | Sep 17, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 16, 2025 | Sep 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 14, 2025 | Nov 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 14, 2025 | Nov 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2025 | Nov 17, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 14, 2025 | Nov 14, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2025 | Dec 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 29, 2025 | Dec 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 29, 2025 | Jan 7, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 29, 2025 | Jan 16, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 29, 2025 | Dec 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 29, 2025 | Dec 31, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 29, 2026 | Jan 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2026 | Feb 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 29, 2026 | Feb 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2026 | Jan 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2026 | Jan 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 4, 2026 | Feb 24, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Michael Bernard Harris Michael Harris Architecture | Architect | C15349 |
| Gordon Leonard Polon | Engineer | C28564 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025