49 Hartford St
San Francisco permit 202411124801 · Castro/Upper Market
Rear addition on 3 levels full kitchen and bathroom remodel. addition of a half bathroom, (n) interior balustrade, new skylights on 3rd floor,new window, upgrade hvac, and add (n) rear deck.
- Filed
- Dec 23, 2024
- Issued
- Aug 21, 2025 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 13 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 12, 2024 | Nov 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 12, 2024 | Nov 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2024 | Nov 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 13, 2024 | Nov 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2024 | Nov 14, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 22, 2024 | Nov 22, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 3, 2024 | Dec 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2024 | Dec 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 24, 2024 | Dec 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 24, 2024 | Feb 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 24, 2024 | Jan 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 24, 2024 | Dec 27, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 24, 2024 | Jan 6, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 24, 2024 | Dec 26, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 24, 2024 | Aug 19, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jan 30, 2025 | Feb 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Feb 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 22, 2025 | Apr 22, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2025 | Apr 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 19, 2025 | May 19, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 28, 2025 | May 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2025 | Jun 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 26, 2025 | Jun 26, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2025 | Jul 21, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 11, 2025 | Aug 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2025 | Aug 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 11, 2025 | Aug 12, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Aug 12, 2025 | Aug 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2025 | Aug 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2025 | Aug 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Jennifer Ly Figure Design | Architect | C38634 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022