CheckMyDesigner

49 Hartford St

San Francisco permit 202411124801 · Castro/Upper Market

AdditionFull plan reviewIssued
Street view · Dec 2022
Google Street View of 49 Hartford St, Dec 2022
Scope of work
As written on the permit application.

Rear addition on 3 levels full kitchen and bathroom remodel. addition of a half bathroom, (n) interior balustrade, new skylights on 3rd floor,new window, upgrade hvac, and add (n) rear deck.

Timeline
Key dates from the city record.
Filed
Dec 23, 2024
Issued
Aug 21, 2025 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
31 stops across 6 departments
Comments issued
13 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Nov 12, 2024Administrative

Zoning review

Planning · CP-ZOC

Nov 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 13, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 13, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 14, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 22, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Dec 20, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Dec 24, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 30, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 7, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 7, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 27, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 6, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Dec 26, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Aug 19, 2025Administrative

Fire prevention review

Fire Department · SFFD

Feb 3, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 5, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Apr 22, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 22, 2025Issued Comments

Building plan review

Building Inspection · BLDG

May 19, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 30, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 12, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 26, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jul 21, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Aug 11, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 11, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 12, 2025Approved-Stipulated

Zoning review

Planning · CP-ZOC

Aug 15, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 13, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 13, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 21, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,200,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jennifer Ly

Figure Design

ArchitectC38634
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202411124801 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record