1828 Egbert Av
San Francisco permit 202411124841 · Bayview Hunters Point
Ti to 1st and 2nd floor. structrural , architectural, mechnanical, and electrical work. site improvements, (n) permiter 8 ft metal fence interior work includes new freezer boxes, site works, includes new refrigration equipment and concrete pad for hvac
- Filed
- Nov 12, 2024
- Issued
- Sep 23, 2025 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 16 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 12, 2024 | Nov 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 31, 2024 | Apr 24, 2025 | Approved |
Public Works disability access review Public Works · PW-DAC | Apr 23, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2025 | Apr 29, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2025 | Apr 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2025 | Apr 30, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2025 | Apr 30, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 5, 2025 | May 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 5, 2025 | May 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2025 | Jun 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2025 | Jul 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2025 | Sep 11, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 22, 2025 | Sep 22, 2025 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $5,000,000
| Name | Role | License on permit |
|---|---|---|
| Ivan Romero | Architect | C12045 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026