650 Howard St
San Francisco permit 202411134883 · Financial District/South Beach
To comply with nov 202426714. sub-sidewalk basement reinforcement.
- Filed
- Dec 3, 2024
- Issued
- Jan 29, 2026 (14 months after filing)
- Completed
- Sep 3, 2026 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 9 stops across 4 departments
- Comments issued
- Twice, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 8, 2024 | Dec 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2024 | Dec 4, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Jan 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 4, 2024 | Dec 30, 2024 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2024 | Dec 11, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 4, 2024 | Jan 16, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | Apr 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2025 | Nov 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 16, 2026 | Jan 29, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $10,000
| Name | Role | License on permit |
|---|---|---|
| Sujin Sung Sujin Sung Engineering | Engineer | C78186 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2025