2646 Great Hy #0
San Francisco permit 202411134905 · Sunset/Parkside
Conversion of open space @ 1/f to a 180sf bedroom and bathroom. remodeling of 135sf kitchen @ 2/f. remodeling of a 57sf bathroom @ 2/f. replace the 2 existing water heaters into a tankless water heaters and relocate to laundry area. add wall and door between the laundry area and garage @ 1/f.
- Filed
- Jan 2, 2025
- Issued
- Aug 18, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 11, 2024 | Dec 3, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 18, 2024 | Jan 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 2, 2025 | Jan 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 3, 2025 | Jul 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 3, 2025 | Feb 24, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 3, 2025 | Jan 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 3, 2025 | Jan 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 3, 2025 | Jan 9, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 3, 2025 | Jul 31, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2025 | Feb 4, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 28, 2025 | Feb 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 28, 2025 | Feb 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 28, 2025 | Feb 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 21, 2025 | Apr 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 22, 2025 | Jun 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 13, 2025 | Jun 16, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 20, 2025 | Jun 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 10, 2025 | Jul 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2025 | Jul 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 29, 2025 | Jul 31, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 29, 2025 | Jul 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2025 | Aug 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $200,700
| Name | Role | License on permit |
|---|---|---|
| Lei Zheng Cecilia Home | Engineer | C69809 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022