Comply w/ dbi internal audit violation# 202418808 rear building expansion, new entry door, and adjacent window. new garage door, replacement windows & skylight. new rear yard stair addition.

Timeline
Key dates from the city record.
Filed
Feb 27, 2025
Issued
Mar 6, 2026 (12 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 6 departments
Comments issued
13 times, by Permit Center, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Nov 20, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 2, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Feb 24, 2025Approved

Building inspector

Building Inspection · BID-INSP

Feb 25, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 27, 2025Administrative

Zoning review

Planning · CP-ZOC

Feb 27, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 7, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 5, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 4, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 5, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Apr 7, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 7, 2025Approved

Permit Processing Center

Building Inspection · PPC

Sep 15, 2025Administrative

Zoning review

Planning · CP-ZOC

May 6, 2025Approved

Building plan review

Building Inspection · BLDG

May 9, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 2, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 5, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 5, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 3, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 7, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 10, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jun 23, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 1, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 23, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 4, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 21, 2025Approved

Zoning review

Planning · CP-ZOC

Aug 22, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 22, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 22, 2025Approved

Urban forestry

Public Works · DPW-BUF

Aug 28, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 27, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 6, 2026Administrative

Building inspector

Building Inspection · BID-INSP

Dec 11, 2025Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$152,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Karen F Curtiss

Red Dot Studio Architecture

ArchitectC31453
Shaun Edward Moynahan

Semco

EngineerS4605
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202411144976 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record