2900 Alemany Bl
San Francisco permit 202411145010 · Outer Mission
Prop h: interior tenant improvements of a vacant grocery store into a bouldering climbing gym. no exterior improvements. renovating to include restroom, locker room, saunas, excercise rooms, structrual improvements. mep under separate permit. cua approval 2024-007292cua. (change of occupupancy).
- Filed
- Mar 18, 2025
- Issued
- Oct 21, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 40 stops across 5 departments
- Comments issued
- 10 times, by Building Inspection, Public Utilities, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 14, 2024 | Nov 14, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 6, 2025 | Mar 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2025 | Mar 6, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 14, 2025 | Mar 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 19, 2025 | Mar 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2025 | Mar 19, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 19, 2025 | Oct 17, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 20, 2025 | Mar 28, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 20, 2025 | Apr 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2025 | Mar 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 21, 2025 | Mar 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2025 | Mar 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2025 | Mar 26, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 26, 2025 | Mar 28, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 28, 2025 | Mar 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2025 | Jul 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 16, 2025 | Jul 22, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jul 16, 2025 | Jul 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 16, 2025 | Jul 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 16, 2025 | Jul 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 21, 2025 | Jul 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 22, 2025 | Jul 23, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 26, 2025 | Aug 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 26, 2025 | Aug 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 26, 2025 | Sep 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 26, 2025 | Aug 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2025 | Sep 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 11, 2025 | Sep 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2025 | Oct 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2025 | Oct 3, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2025 | Oct 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2025 | Oct 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 9, 2025 | Oct 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2025 | Oct 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 10, 2025 | Oct 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 14, 2025 | Oct 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 14, 2025 | Oct 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 16, 2025 | Oct 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2025 | Oct 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2025 | Oct 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Russell M Beaudin Twelves 13 Architecture | Architect | C26255 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022