65 Division St
San Francisco permit 202411155106 · Mission Bay
Remodel (e) outdoor restaurant patio to include (n) partially covered outdoor bar & upgraded exterior canopy structure. remodel interior of (e) restaurant with (n) kitchen equipment & lighting
- Filed
- Nov 15, 2024
- Issued
- Apr 9, 2025 (5 months after filing)
- Completed
- Mar 27, 2026 (12 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 20 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Nov 14, 2024 | Nov 14, 2024 | Approved |
Building inspector Building Inspection · BID-INSP | Nov 15, 2024 | Nov 15, 2024 | Approved |
Intake Building Inspection · INTAKE | Nov 15, 2024 | Nov 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 15, 2024 | Nov 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 18, 2024 | Nov 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2024 | Nov 18, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 18, 2024 | Nov 18, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 19, 2024 | Nov 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 6, 2024 | Dec 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2024 | Dec 6, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 13, 2025 | Jan 13, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 23, 2025 | Jan 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2025 | Jan 24, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 31, 2025 | Jan 31, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 31, 2025 | Jan 31, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 31, 2025 | Jan 31, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 3, 2025 | Feb 3, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Feb 3, 2025 | Feb 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 7, 2025 | Feb 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2025 | Apr 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $760,000
| Name | Role | License on permit |
|---|---|---|
| Heidi Lee Liebes Lieves Architects | Architect | C29300 |
| Alexis Lawrence Rood Pivot | Engineer | S4492 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026