461 Anderson St
San Francisco permit 202411155136 · Bernal Heights
1/f: replace garage door, enclose lightwell, remodel (e) bathroom, family room/den, add mudroom & storage room. 2/f: enclose (e) lightwell, add half bath, relocate (e) full bathroom, remodel kitchen.
- Filed
- Apr 14, 2025
- Issued
- Aug 28, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 4 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 15, 2024 | Nov 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 15, 2024 | Nov 15, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Mar 27, 2025 | Mar 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 27, 2025 | Mar 27, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 28, 2025 | Apr 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2025 | Apr 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 15, 2025 | May 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2025 | May 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2025 | May 26, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 15, 2025 | Apr 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2025 | Apr 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2025 | Apr 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 15, 2025 | Jul 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 25, 2025 | Jun 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2025 | Jun 26, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 25, 2025 | Jul 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 25, 2025 | Jul 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2025 | Jul 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 25, 2025 | Jul 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2025 | Jul 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2025 | Jul 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 29, 2025 | Aug 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $268,000
| Name | Role | License on permit |
|---|---|---|
| Karen Mar Marjang Design | Payor | C25227 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023