1555 Yosemite Av #4
San Francisco permit 202411185168 · Bayview Hunters Point
Unit #4: new office and open office partitions and work surfaces. selected bathroom new floor and wall finishes, 2 new doors. upgrade of primary entrance door hardware and interior landing/threshold. replace (e) plumbing fixtures to meet curret code.
- Filed
- Nov 18, 2024
- Issued
- Jan 9, 2025 (2 months after filing)
- Completed
- Nov 3, 2025 (10 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 11 stops across 5 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 18, 2024 | Nov 18, 2024 | Administrative |
Intake Building Inspection · INTAKE | Dec 17, 2024 | Dec 17, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 17, 2024 | Dec 17, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Dec 17, 2024 | Dec 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2024 | Dec 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 17, 2024 | Dec 17, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2024 | Dec 17, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 18, 2024 | Dec 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 18, 2024 | Dec 18, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 31, 2024 | Dec 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2025 | Jan 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $36,800
| Name | Role | License on permit |
|---|---|---|
| Christian J Dauer Chr Dauer Architect | Architect | C28302 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022