1201 12th Av #0
San Francisco permit 202411195326 · Inner Sunset
Rev pa201902082492 -reduction of original socpe from 5 adu to 4 adu.reconfigure garages (5) on g/f to become 4 adu. horizontal extension of side light court.
- Filed
- Jan 7, 2025
- Issued
- Jun 18, 2025 (5 months after filing)
- Completed
- Aug 20, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 15, 2024 | Dec 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 19, 2024 | Nov 19, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 10, 2024 | Dec 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2025 | Jan 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 7, 2025 | Jan 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 7, 2025 | Jan 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2025 | Jan 30, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 7, 2025 | Jan 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 7, 2025 | Jan 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 7, 2025 | Jan 9, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 7, 2025 | Feb 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2025 | Jan 13, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 7, 2025 | Apr 23, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Feb 20, 2025 | Feb 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 28, 2025 | Mar 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2025 | Mar 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2025 | Mar 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 7, 2025 | Mar 10, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2025 | Mar 13, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 11, 2025 | Mar 11, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 17, 2025 | Mar 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2025 | Apr 3, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 4, 2025 | Apr 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 4, 2025 | Apr 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2025 | Jun 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Serina L Calhoun Syncopated Architecture | Architect | C-30744 |
| Ali Afrasiabi Rei Build Up Design | Engineer | S-5413 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015