237 04th Av
San Francisco permit 202411205358 · Inner Richmond
Interior remodel: (n) family room, office, bath, laundry room at 1st floor. remodel kitchen and half bath at 2nd floor, remodel (2) baths at 3rd floor. shared plans w/ pa# 202411205361
- Filed
- Dec 11, 2024
- Issued
- Mar 17, 2025 (3 months after filing)
- Completed
- May 4, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 19 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 20, 2024 | Nov 20, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 20, 2024 | Nov 20, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Nov 25, 2024 | Dec 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2024 | Dec 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 12, 2024 | Jan 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2024 | Feb 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 12, 2024 | Dec 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2024 | Jan 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2024 | Dec 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 12, 2024 | Feb 28, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Feb 4, 2025 | Feb 4, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 10, 2025 | Feb 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2025 | Feb 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2025 | Feb 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2025 | Feb 26, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 11, 2025 | Feb 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2025 | Feb 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 19, 2025 | Feb 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 28, 2025 | Mar 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Aaron Michael Lim Aaron Lim Design | Architect | C37034 |
| Erik Mcgregor Wmstructural | Engineer | S6802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025