CheckMyDesigner

237 04th Av

San Francisco permit 202411205358 · Inner Richmond

Home remodelFull plan reviewComplete
Street view · Feb 2025
Google Street View of 237 04th Av, Feb 2025
Scope of work
As written on the permit application.

Interior remodel: (n) family room, office, bath, laundry room at 1st floor. remodel kitchen and half bath at 2nd floor, remodel (2) baths at 3rd floor. shared plans w/ pa# 202411205361

Timeline
Key dates from the city record.
Filed
Dec 11, 2024
Issued
Mar 17, 2025 (3 months after filing)
Completed
May 4, 2026 (14 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
19 stops across 6 departments
Comments issued
3 times, by Building Inspection, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Nov 20, 2024Administrative

Zoning review

Planning · CP-ZOC

Nov 20, 2024Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Dec 11, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Dec 12, 2024Administrative

Building plan review

Building Inspection · BLDG

Jan 29, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 11, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 13, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jan 15, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 20, 2024Approved

Permit Processing Center

Building Inspection · PPC

Feb 28, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Feb 4, 2025Administrative

Fire prevention review

Fire Department · SFFD

Feb 11, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 11, 2025Approved

Building plan review

Building Inspection · BLDG

Feb 18, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Feb 26, 2025Approved

Fire prevention review

Fire Department · SFFD

Feb 14, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 25, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 19, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 17, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$600,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Aaron Michael Lim

Aaron Lim Design

ArchitectC37034
Erik Mcgregor

Wmstructural

EngineerS6802
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202411205358 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record