3575 Clay St
San Francisco permit 202411265790 · Presidio Heights
New dormer. fill in 56 sq ft on level 1. demo e construct new partitons, structural and non structural . excavate basement and add new rooms. removel and add new baths and kitchen. new lighting and electrical.
- Filed
- Dec 24, 2024
- Issued
- May 20, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 7 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 26, 2024 | Nov 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 2, 2024 | Dec 2, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 2, 2024 | Dec 2, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Dec 2, 2024 | Dec 2, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 4, 2024 | Dec 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2024 | Dec 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 26, 2024 | Dec 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 26, 2024 | Feb 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 26, 2024 | Jan 9, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 26, 2024 | Dec 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2024 | Dec 26, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 26, 2024 | Feb 11, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2024 | Jan 8, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 26, 2024 | May 5, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Feb 26, 2025 | Mar 24, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2025 | Feb 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 28, 2025 | Feb 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 4, 2025 | Mar 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2025 | Mar 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2025 | Mar 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 25, 2025 | Mar 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2025 | Mar 26, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 4, 2025 | Apr 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 7, 2025 | Apr 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 5, 2025 | May 20, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey O Graham Graham Architects | Architect | C22806 |
| Diarmuid Hugo Mac Neill Dolmen Structural Engineer | Engineer | C56739 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020