1250 Chestnut St #0
San Francisco permit 202411275819 · Russian Hill
Ground floor: add a proposed 1-bed replacement dwelling unit. 2nd flr: merge and remodel 2 existing 1-bed dwelling units into one proposed 3-bedroom dwelling unit. 3rd floor: remodel the existing 3rd fl. unit kitchen and bath; add one full bath. uprade/replace -in - kind exiting windows throughout
- Filed
- Nov 27, 2024
- Issued
- Feb 14, 2025 (3 months after filing)
- Completed
- Jun 5, 2026 (16 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 12 stops across 5 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Nov 27, 2024 | Nov 27, 2024 | Approved |
Intake Building Inspection · INTAKE | Nov 27, 2024 | Nov 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 27, 2024 | Nov 27, 2024 | Approved |
Intake Building Inspection · INTAKE | Dec 18, 2024 | Dec 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 18, 2024 | Dec 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 19, 2024 | Dec 19, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 19, 2024 | Dec 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2024 | Dec 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 19, 2024 | Dec 19, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2024 | Dec 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 20, 2024 | Dec 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2025 | Feb 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $449,934
| Name | Role | License on permit |
|---|---|---|
| Andrew Ross Levine Levine Architect | Architect | C-14090 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025