3900 03rd St
San Francisco permit 202412035993 · Bayview Hunters Point
Renov. of shared bathrooms @ lvls 2&3. convert (e) g.f. retail space to support services for (p) boarding rms abv. legalize 1 sleeping room (307) for a total of 20 sleeping rms. energy upgrades incl: (n) lighting and mechanical units. replce all int. flooring, cabinets,plumbing fixtures and finishes
- Filed
- Mar 10, 2025
- Issued
- Jul 1, 2025 (4 months after filing)
- Completed
- Apr 1, 2026 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 21 stops across 5 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 2, 2024 | Dec 13, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2024 | Mar 11, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Feb 19, 2025 | Mar 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 11, 2025 | Mar 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2025 | Mar 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2025 | Mar 20, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 11, 2025 | Mar 25, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2025 | Mar 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 11, 2025 | Jun 18, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Mar 19, 2025 | Mar 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 16, 2025 | Apr 17, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2025 | Apr 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 2, 2025 | May 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2025 | May 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jun 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 9, 2025 | Jun 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 10, 2025 | Jun 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 11, 2025 | Jun 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2025 | Jun 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2025 | Jun 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 18, 2025 | Jul 1, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,365,000
| Name | Role | License on permit |
|---|---|---|
| David Brady Smith Lpas Architecture + Design | Architect | C30082 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026