CheckMyDesigner

3900 03rd St

San Francisco permit 202412035993 · Bayview Hunters Point

Commercial or tenant improvement (type unconfirmed)Full plan reviewComplete
Street view · Sep 2026
Google Street View of 3900 03rd St, Sep 2026
Scope of work
As written on the permit application.

Renov. of shared bathrooms @ lvls 2&3. convert (e) g.f. retail space to support services for (p) boarding rms abv. legalize 1 sleeping room (307) for a total of 20 sleeping rms. energy upgrades incl: (n) lighting and mechanical units. replce all int. flooring, cabinets,plumbing fixtures and finishes

Timeline
Key dates from the city record.
Filed
Mar 10, 2025
Issued
Jul 1, 2025 (4 months after filing)
Completed
Apr 1, 2026 (9 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
21 stops across 5 departments
Comments issued
8 times, by Permit Center, Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 13, 2024Issued Comments

Central Permit Bureau

Building Inspection · CPB

Mar 11, 2025Administrative

Permit Center

Permit Center · PERMIT-CTR

Mar 7, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 25, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 18, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 20, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 25, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 14, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jun 18, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Mar 19, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 17, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 22, 2025Issued Comments

Building plan review

Building Inspection · BLDG

May 19, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 20, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 3, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jun 9, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 10, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 12, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 18, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 13, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 1, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$1,365,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David Brady Smith

Lpas Architecture + Design

ArchitectC30082
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202412035993 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record