182 Eureka St
San Francisco permit 202412046156 · Castro/Upper Market
Basement: new reinforced foundation and slab to replace (e) brick foundation (84lf) and slab.(e) wood supporting beam replaced w/steel beam.(n) conditioned,non-habitable full bath within garage and (n) storage addition @ rear.build out corner so garage door can be widened.1/f:unconditioned...
- Filed
- Jan 9, 2025
- Issued
- Jun 5, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 29 stops across 6 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 3, 2024 | Dec 13, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 17, 2024 | Dec 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2024 | Jan 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 9, 2025 | Jan 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2025 | Feb 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2025 | Jan 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 9, 2025 | Jan 10, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2025 | Jan 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2025 | Jan 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 9, 2025 | Apr 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 4, 2025 | Feb 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2025 | Feb 6, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2025 | Feb 6, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2025 | Feb 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 4, 2025 | Feb 7, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 25, 2025 | Feb 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 25, 2025 | Mar 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2025 | Mar 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2025 | Apr 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2025 | Mar 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2025 | Mar 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2025 | Apr 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2025 | Apr 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2025 | Apr 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2025 | Apr 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2025 | Apr 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2025 | Apr 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2025 | Jun 5, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $720,000
| Name | Role | License on permit |
|---|---|---|
| Joseph Z Armin Jza Architure | Architect | C33004 |
| Ricardo Gonzalez Pivot | Engineer | C-58960 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2021