45 Mccoppin St
San Francisco permit 202412056251 · Mission
To comply w/nov# 202309140, document existing and unpermitted conditions; provide a rated fire wall and window sprinkler protection/ replacement to provide compliant roof exiting; provide rated parapets and roof fire protection features; construct interior framed walls and ceilings to atmoshpericall
- Filed
- Dec 30, 2024
- Issued
- Feb 10, 2026 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 4, 2024 | Dec 23, 2024 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Dec 23, 2024 | Dec 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2024 | Dec 31, 2024 | Administrative |
Code enforcement Building Inspection · CES | Dec 31, 2024 | Jan 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 31, 2024 | Jan 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 31, 2024 | Feb 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 31, 2024 | Jan 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 31, 2024 | Jan 22, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 31, 2024 | Feb 2, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Oct 6, 2025 | Nov 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2025 | Oct 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 20, 2025 | Nov 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 24, 2025 | Nov 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 22, 2025 | Dec 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 30, 2025 | Dec 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2026 | Jan 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 20, 2026 | Jan 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2026 | Feb 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $38,000
| Name | Role | License on permit |
|---|---|---|
| Edward Davis Morris Kerman Morris Architects | Architect | C24585 |
| Lisa Wai Sum Tse Integrand Structural Engineer | Engineer | 4839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025