3318 Fillmore St
San Francisco permit 202412106460 · Marina
Two new retractable roofs at an existing 2-story building. rooftop hvac unit relocate and duct system extension for (e) restaurant space. no change of use, occupant load, height, and area.
| Fact | Before | After |
|---|---|---|
| Use | Food/beverage hndlng | No change |
| Stories | 2 | No change |
- Filed
- Sep 22, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 23 stops across 5 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 8, 2024 | Dec 23, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Dec 10, 2024 | Sep 22, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Apr 4, 2025 | Apr 21, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 5, 2025 | Sep 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 22, 2025 | Oct 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2025 | Oct 27, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 22, 2025 | Oct 16, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2025 | Oct 22, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 22, 2025 | Oct 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 22, 2025 | Dec 23, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 22, 2025 | In progress | — |
Public health review Public Health · HEALTH | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Sep 23, 2025 | Sep 30, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Oct 27, 2025 | Oct 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 5, 2026 | Mar 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2026 | Mar 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 16, 2026 | Mar 16, 2026 | Approved-Stipulated |
Electrical plan review Building Inspection · MECH-E | Apr 6, 2026 | Apr 6, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 9, 2026 | Apr 9, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2026 | Apr 30, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Apr 29, 2026 | May 12, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | May 21, 2026 | May 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $13,500
| Name | Role | License on permit |
|---|---|---|
| Wing Kin Lee Wing Lee Architects | Architect | C28929 |
| Lou Xiao Lx Engineering | Engineer | S5130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025