CheckMyDesigner

506 Gates St

San Francisco permit 202412116574 · Bernal Heights

AdditionFull plan reviewReinstated
Street view · Dec 2017
Google Street View of 506 Gates St, Dec 2017
Scope of work
As written on the permit application.

Two story addition to front east elevation add 1 bath remodel 2 bath re-configure kitchen.

Timeline
Key dates from the city record.
Filed
Jan 7, 2025
Issued
Sep 29, 2025 (9 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 6 departments
Comments issued
7 times, by Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 27, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jan 7, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 30, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 24, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 30, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jan 15, 2025Approved

Permit Processing Center

Building Inspection · PPC

Aug 6, 2025Administrative

Building plan review

Building Inspection · BLDG

Mar 14, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Apr 25, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 18, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Apr 18, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 3, 2025Not Applicable

Structural plan approval

Building Inspection · PAD-STR

Apr 18, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Apr 28, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Apr 21, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 24, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Aug 6, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 27, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 2, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jul 9, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 8, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 8, 2025Administrative

Building plan review

Building Inspection · BLDG

Aug 5, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jul 17, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jul 23, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 17, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 23, 2025Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Jul 21, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Sep 29, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Reinstated
Estimated cost
$300,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Fallon Lee James

Studio Fallon Architecture

Authorized agent-othersC39746
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202412116574 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record