As written on the permit application.

T.i. for existing financial banking center. no additional height is past of the scope. scope included new non-load bearing partitions, load beariing gravity columns, exterior glazing, floor finishes, ceiling, millworks, lighting, plumbing, hvac distribution, lefe safety, system accessible parking

Timeline
Key dates from the city record.
Filed
Feb 12, 2025
Issued
May 23, 2025 (3 months after filing)
Completed
Dec 22, 2025 (7 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 5 departments
Comments issued
8 times, by Building Inspection, Permit Center, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Dec 11, 2024Administrative

Zoning review

Planning · CP-ZOC

May 1, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 11, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Dec 11, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Dec 31, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 31, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 12, 2025Administrative

Building plan review

Building Inspection · BLDG

Feb 28, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 17, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 25, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 3, 2025Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Feb 12, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

May 19, 2025Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Feb 14, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Mar 13, 2025Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Mar 7, 2025Administrative

Building Inspection

MECH-E-QC

Mar 20, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 25, 2025Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Mar 25, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 18, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Mar 28, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 1, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Apr 11, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 14, 2025Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Apr 15, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Apr 25, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 28, 2025Administrative

Fire prevention review

Fire Department · SFFD

Apr 28, 2025Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Apr 28, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 29, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 2, 2025Approved

Building plan review

Building Inspection · BLDG

May 14, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 23, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$3,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jeffrey A Schmierer

Gensler

ArchitectC29750
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202412116614 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record