3533 California St
San Francisco permit 202412116614 · Presidio Heights
T.i. for existing financial banking center. no additional height is past of the scope. scope included new non-load bearing partitions, load beariing gravity columns, exterior glazing, floor finishes, ceiling, millworks, lighting, plumbing, hvac distribution, lefe safety, system accessible parking
- Filed
- Feb 12, 2025
- Issued
- May 23, 2025 (3 months after filing)
- Completed
- Dec 22, 2025 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 33 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Permit Center, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 11, 2024 | Dec 11, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 11, 2024 | May 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 11, 2024 | Dec 11, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 11, 2024 | Dec 11, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 17, 2024 | Dec 31, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 16, 2025 | Jan 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2025 | Feb 12, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Feb 28, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2025 | Mar 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2025 | Mar 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 12, 2025 | Mar 3, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2025 | Feb 12, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 12, 2025 | May 19, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2025 | Feb 14, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 3, 2025 | Mar 13, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 7, 2025 | Mar 7, 2025 | Administrative |
Building Inspection MECH-E-QC | Mar 17, 2025 | Mar 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2025 | Mar 25, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2025 | Mar 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Apr 18, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 28, 2025 | Mar 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 1, 2025 | Apr 1, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 10, 2025 | Apr 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 14, 2025 | Apr 14, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2025 | Apr 15, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 25, 2025 | Apr 25, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 28, 2025 | Apr 28, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 28, 2025 | Apr 28, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2025 | Apr 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 2, 2025 | May 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 2, 2025 | May 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 19, 2025 | May 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $3,500,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey A Schmierer Gensler | Architect | C29750 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026