1443 A Broderick St
San Francisco permit 202412136782 · Japantown
Permitting of (e) unpermitted adu on basement level constructed w/o permits. to meet code, updated to provide a casement windows from the sleeping area for egress and a 7-6" ceiling throughout the egress corridor to the street. planting of (n) street tree on sidewalk.
- Filed
- Feb 5, 2025
- Issued
- Jul 18, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 10 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2024 | Dec 24, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 21, 2025 | Jan 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 5, 2025 | Feb 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 5, 2025 | Feb 19, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Feb 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 5, 2025 | Feb 10, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2025 | Feb 6, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 5, 2025 | Feb 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2025 | Feb 6, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 5, 2025 | Jul 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 9, 2025 | Apr 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 9, 2025 | Apr 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2025 | Apr 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 9, 2025 | Apr 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2025 | Apr 10, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 9, 2025 | Apr 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 9, 2025 | Apr 23, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 8, 2025 | May 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2025 | May 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2025 | May 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 8, 2025 | May 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2025 | May 12, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 8, 2025 | May 28, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2025 | May 12, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 3, 2025 | Jul 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2025 | Jul 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $159,999
| Name | Role | License on permit |
|---|---|---|
| Matthew Alexander Ininns Mist Architects | Architect | C37517 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026