211 Jefferson St

San Francisco permit 202412176961 · North Beach

Commercial or tenant improvementFull plan reviewComplete
Street view · Sep 2026
Google Street View of 211 Jefferson St, Sep 2026
Scope of work
As written on the permit application.

Change of use a3 to a2 occupancy-partial demo, renovation and conversion of 1st floor of (e) 3 story building from gallery to restaurant. (n) work includes remodel of 1st floor, mep work, minor structural scope, minor exterior storefront and utility improvements

Timeline
Key dates from the city record.
Filed
May 12, 2025
Issued
Nov 7, 2025 (6 months after filing)
Completed
Oct 28, 2026 (12 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
41 stops across 7 departments
Comments issued
7 times, by Fire Department, Permit Center, Building Inspection, Public Health
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Dec 17, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 17, 2024Not Applicable

Building plan review

Building Inspection · BLDG

Dec 17, 2024Approved

Fire prevention review

Fire Department · SFFD

Dec 17, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 17, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 18, 2024Approved

Intake

Building Inspection · INTAKE

Jan 8, 2025Administrative

Electrical plan review

Building Inspection · MECH-E

Jan 8, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jan 8, 2025Approved

Permit Center

Permit Center · PERMIT-CTR

Jan 31, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Apr 7, 2025Issued Comments

Central Permit Bureau

Building Inspection · CPB

May 12, 2025Administrative

Permit Center

Permit Center · PERMIT-CTR

Apr 30, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 3, 2025Issued Comments

Electrical plan review

Building Inspection · MECH-E

May 20, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 22, 2025Approved

Street use and mapping

Public Works · DPW-BSM

May 19, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 20, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

May 20, 2025Approved-Stipulated

Public health food review

Public Health · HEALTH-FD

May 13, 2025Administrative

Public health food review

Public Health · HEALTH-FD

May 27, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Oct 3, 2025Administrative

Public Health

HEALTH-HM

May 15, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 15, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 19, 2025Issued Comments

Electrical plan review

Building Inspection · MECH-E

Aug 15, 2025Approved

Fire prevention review

Fire Department · SFFD

Oct 3, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 21, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 18, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Aug 18, 2025Approved-Stipulated

Public health food review

Public Health · HEALTH-FD

Aug 21, 2025Approved

Public Health

HEALTH-HM

Aug 15, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 26, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 29, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Sep 26, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 1, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 29, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Sep 29, 2025Approved

Public health food review

Public Health · HEALTH-FD

Oct 3, 2025Approved

Public Health

HEALTH-HM

Sep 25, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 7, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$6,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Kenneth Mccracken

Pm Design Architectural

ArchitectC32095
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202412176961 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record