441 Madrid St
San Francisco permit 202412176994 · Excelsior
Replacement of beam and posts on g/f. legalize conditioned space. repair slab and relocate g/f bathroom ext staircase replacement. wdws and ext sheathing replacement of rear elevation. (n) g/f lighting, power, hvac and plumbing. new 1hr wall at replaced ext staircase.
- Filed
- Feb 22, 2025
- Issued
- Feb 19, 2026 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 43 stops across 6 departments
- Comments issued
- 7 times, by Permit Center, Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 16, 2024 | Dec 27, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 6, 2025 | Jan 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2025 | Feb 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 24, 2025 | Feb 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 24, 2025 | Mar 24, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 24, 2025 | Mar 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2025 | Apr 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 24, 2025 | Feb 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2025 | Mar 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2025 | Mar 5, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 24, 2025 | Dec 2, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2025 | Mar 7, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 19, 2025 | Mar 24, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 25, 2025 | Nov 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2025 | Jul 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2025 | Jun 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2025 | Jul 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 25, 2025 | Jul 1, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2025 | Jun 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2025 | Jun 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 22, 2025 | Aug 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2025 | Sep 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 22, 2025 | Aug 22, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2025 | Aug 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2025 | Aug 25, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2025 | Sep 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 28, 2025 | Sep 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2025 | Sep 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2025 | Sep 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 19, 2025 | Sep 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2025 | Oct 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 19, 2025 | Sep 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 19, 2025 | Sep 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2025 | Sep 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 14, 2025 | Oct 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 13, 2025 | Nov 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2025 | Nov 24, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 13, 2025 | Nov 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2025 | Dec 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 13, 2025 | Nov 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 13, 2025 | Nov 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2025 | Nov 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 2, 2025 | Feb 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $156,947
| Name | Role | License on permit |
|---|---|---|
| Bo Zhang Disseny : Llora | Engineer | C82956 |
| Donald David Double D Engineering | Engineer | S-3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011