Replacement of beam and posts on g/f. legalize conditioned space. repair slab and relocate g/f bathroom ext staircase replacement. wdws and ext sheathing replacement of rear elevation. (n) g/f lighting, power, hvac and plumbing. new 1hr wall at replaced ext staircase.

Timeline
Key dates from the city record.
Filed
Feb 22, 2025
Issued
Feb 19, 2026 (12 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
43 stops across 6 departments
Comments issued
7 times, by Permit Center, Building Inspection, Fire Department, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 27, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 22, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 24, 2025Administrative

Zoning review

Planning · CP-ZOC

Feb 24, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 24, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 18, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 5, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 25, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 4, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 5, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Dec 2, 2025Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Mar 7, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Mar 24, 2025Approved

Zoning review

Planning · CP-ZOC

Nov 12, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 18, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 11, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 1, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jun 26, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 27, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 5, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 22, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 25, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 25, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 2, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 4, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 8, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 3, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 23, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 2, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 30, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 24, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 23, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 14, 2025Approved

Zoning review

Planning · CP-ZOC

Nov 20, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 24, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 20, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 1, 2025Approved

Fire prevention review

Fire Department · SFFD

Nov 20, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Nov 17, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 14, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 19, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$156,947
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Bo Zhang

Disseny : Llora

EngineerC82956
Donald David

Double D Engineering

EngineerS-3928
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202412176994 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record