Remodel (e) kitchen, powder/laundry room. demo (e) bay window & replace w/door. new rear yard deck & stairs. (e) windows replace in kind. new master bath & closet. remodel (e) bath & skylight. voluntary seismic retrofit
- Filed
- Jan 15, 2025
- Issued
- Apr 14, 2025 (3 months after filing)
- Completed
- Aug 20, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 18, 2024 | Dec 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 18, 2024 | Dec 18, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 26, 2024 | Jan 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 15, 2025 | Jan 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 15, 2025 | Jan 16, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 15, 2025 | Feb 18, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 15, 2025 | Feb 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 15, 2025 | Jan 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2025 | Jan 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2025 | Jan 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 15, 2025 | Apr 4, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 6, 2025 | Mar 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 6, 2025 | Mar 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2025 | Mar 7, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 6, 2025 | Mar 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 6, 2025 | Mar 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2025 | Mar 12, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 19, 2025 | Mar 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Mar 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 1, 2025 | Apr 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 2, 2025 | Apr 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2025 | Apr 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 2, 2025 | Apr 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2025 | Apr 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 4, 2025 | Apr 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $218,219
| Name | Role | License on permit |
|---|---|---|
| Michael Storer | Engineer | C84865 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026