75 Brosnan St
San Francisco permit 202412187050 · Mission
To comply with complaint# 202431214. repair stairs by replacing posts, foundations and install new guardrail and handrail. repair in-kind <50%.
- Filed
- Dec 18, 2024
- Issued
- Jan 7, 2025 (within 1 month of filing)
- Completed
- Mar 4, 2025 (2 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 5 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Dec 18, 2024 | Dec 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 18, 2024 | Dec 18, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Dec 18, 2024 | Dec 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 19, 2024 | Dec 19, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2025 | Jan 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $6,000
| Name | Role | License on permit |
|---|---|---|
| Andy Tan Andy Tan | Engineer | C-70119 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022