740 Sanchez St
San Francisco permit 202412207184 · Castro/Upper Market
Renovation of existing single family residence. addition of new story and roof deck. approved variance for rear yard setback. approved conditional use authorization (2024-001470cua) for veritical addition in central neighborhood large residence special use district.
- Filed
- Dec 24, 2024
- Issued
- Dec 31, 2024 (within 1 month of filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 44 stops across 6 departments
- Comments issued
- 12 times, by Planning, Building Inspection, Fire Department, Permit Center, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 18, 2024 | Dec 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2024 | Dec 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 26, 2024 | Dec 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 26, 2024 | Dec 27, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 26, 2024 | Dec 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 26, 2024 | Dec 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2024 | Dec 30, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2024 | Dec 27, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 26, 2024 | Dec 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 30, 2024 | Dec 30, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 30, 2024 | Dec 31, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Dec 31, 2024 | Dec 31, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 31, 2024 | Dec 31, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 31, 2024 | Dec 31, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2024 | Dec 31, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2024 | Dec 31, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 31, 2024 | Dec 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 31, 2024 | Dec 31, 2024 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 17, 2025 | Jan 31, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 20, 2025 | Mar 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2025 | Mar 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 6, 2025 | Mar 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2025 | Mar 25, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 6, 2025 | Mar 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2025 | Mar 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 6, 2025 | Mar 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 6, 2025 | Mar 10, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 6, 2025 | May 5, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2025 | Mar 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 6, 2025 | Jun 11, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2025 | Apr 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 18, 2025 | Apr 28, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 28, 2025 | Apr 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 23, 2025 | May 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 27, 2025 | Jun 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 28, 2025 | Jun 4, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 28, 2025 | May 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 2, 2025 | Jun 2, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2025 | Jun 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 4, 2025 | Jun 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2025 | Jun 4, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 6, 2025 | Jun 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 11, 2025 | Jun 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $822,194
| Name | Role | License on permit |
|---|---|---|
| Gregory K Iboshi Huang Iboshi Architecture Inc | Payor | C27547 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020