550 Terry A Francois Bl
San Francisco permit 202412247379 · Mission Bay
Structural slab openings and perimeter shaft walls: (2) shaft wall locations at level 1; (2) slab opening and shaft wall location at level 2; (1) slab opening and shaft wall locations at level 3 thru 6
- Filed
- Jan 28, 2025
- Issued
- May 6, 2025 (3 months after filing)
- Completed
- Aug 12, 2026 (15 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 15 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 24, 2024 | Dec 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 6, 2025 | Jan 6, 2025 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Jan 13, 2025 | Jan 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Jan 28, 2025 | Administrative |
Redevelopment review Redevelopment · REDEV | Jan 28, 2025 | Jan 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Feb 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2025 | Mar 13, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 28, 2025 | Feb 11, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Jan 28, 2025 | Apr 28, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Mar 11, 2025 | Mar 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 26, 2025 | Apr 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2025 | Apr 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2025 | Apr 21, 2025 | Approved |
Redevelopment review Redevelopment · REDEV | Apr 21, 2025 | Apr 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 28, 2025 | May 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $694,000
| Name | Role | License on permit |
|---|---|---|
| Patrick Robert Daly Woods Bagot | Architect | C29703 |
| Paul Anthony Littler Holmes Structural | Engineer | S6189 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026