638 Rhode Island St
San Francisco permit 202412277452 · Potrero Hill
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
(n) exterior deck, (n) exterior stair to (n) 3rd fl deck, (n) roof deck, (n) spiral stair to (n) roof deck, (n) window and (n) door at 3rd fl. ref pa# 2023-0203-1391 for additional scope of work to 3rd fl.
- Filed
- Mar 11, 2025
- Issued
- Jul 17, 2025 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Dec 27, 2024 | Dec 27, 2024 | — |
Building inspector Building Inspection · BID-INSP | Dec 27, 2024 | Dec 27, 2024 | — |
Code enforcement Building Inspection · CES | Dec 27, 2024 | Dec 27, 2024 | — |
Intake Building Inspection · INTAKE | Dec 27, 2024 | Dec 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 27, 2024 | Dec 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 27, 2024 | Dec 27, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2025 | Feb 11, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 21, 2025 | Feb 21, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 24, 2025 | Mar 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2025 | Mar 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 12, 2025 | Jul 14, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 12, 2025 | Mar 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2025 | Apr 13, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 12, 2025 | Apr 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 12, 2025 | Jul 15, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 20, 2025 | Apr 21, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 15, 2025 | Jun 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 2, 2025 | Jul 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 10, 2025 | Jul 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2025 | Jul 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 11, 2025 | Jul 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 15, 2025 | Jul 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Johnston Rodgers Rodgers Architecture | Architect | C30697 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025