2083 Union St
San Francisco permit 202412307495 · Marina
Interior t.i. of e) retail outlet included interior demo, finishes, lighting, fixture & minor electrical, no change of use or tenant
- Filed
- Apr 14, 2025
- Issued
- Aug 11, 2025 (4 months after filing)
- Completed
- Feb 10, 2026 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 37 stops across 4 departments
- Comments issued
- 13 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 30, 2024 | Dec 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 30, 2024 | Dec 30, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Dec 30, 2024 | Dec 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 30, 2024 | Dec 30, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 2, 2025 | Jan 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 5, 2025 | Feb 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Feb 5, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 5, 2025 | Feb 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 26, 2025 | Feb 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 27, 2025 | Feb 27, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 27, 2025 | Feb 27, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 17, 2025 | Mar 17, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 17, 2025 | Mar 17, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 24, 2025 | Apr 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2025 | Apr 15, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 15, 2025 | Apr 28, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 15, 2025 | Apr 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2025 | Apr 25, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 15, 2025 | Apr 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2025 | Apr 15, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 15, 2025 | Aug 6, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2025 | Apr 22, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2025 | Apr 24, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Apr 28, 2025 | Apr 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2025 | Apr 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 7, 2025 | May 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2025 | Jun 4, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 5, 2025 | Jun 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 12, 2025 | Jun 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 27, 2025 | Jun 27, 2025 | Approved |
Building Inspection MECH-E-QC | Jul 11, 2025 | Jul 11, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jul 30, 2025 | Jul 30, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 30, 2025 | Jul 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 31, 2025 | Aug 1, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2025 | Aug 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2025 | Jul 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2025 | Aug 11, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $943,071
| Name | Role | License on permit |
|---|---|---|
| Brian C Perlow | Architect | C33266 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026