774 Tehama St
San Francisco permit 202412307532 · South of Market
Demo and reconstruction of second story and restrooms in response to the following notice of violations:nov#'s: 202425066, 202425811, and 202425824.scope of work is interior only.
- Filed
- Apr 19, 2025
- Issued
- Apr 8, 2026 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 32 stops across 4 departments
- Comments issued
- 13 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 20, 2024 | Jan 6, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 23, 2025 | Feb 5, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 3, 2025 | Apr 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2025 | Apr 21, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 21, 2025 | Jun 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 21, 2025 | Jun 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2025 | Jun 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 21, 2025 | Apr 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 21, 2025 | May 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 21, 2025 | Mar 16, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jun 6, 2025 | Jun 6, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 24, 2025 | Jun 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2025 | Aug 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2025 | Aug 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 11, 2025 | Aug 11, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2025 | Aug 14, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Aug 20, 2025 | Aug 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 28, 2026 | Jan 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2026 | Feb 5, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 4, 2026 | Feb 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2026 | Feb 5, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2026 | Feb 5, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 12, 2026 | Feb 12, 2026 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Feb 17, 2026 | Feb 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 25, 2026 | Feb 25, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2026 | Feb 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 27, 2026 | Feb 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 2, 2026 | Mar 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 6, 2026 | Mar 16, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 6, 2026 | Mar 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2026 | Apr 8, 2026 | Administrative |
Code enforcement Building Inspection · CES | Mar 27, 2026 | Mar 27, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $329,577
| Name | Role | License on permit |
|---|---|---|
| Austen Boyd Diliberto | Architect | C36278 |
| Lou Xiao Lx Engineering | Engineer | S5130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025