Rehab fire damaged 24-units residential building & address abataement #202311915a. get final approval for 4-adus approved- ref pa# 201717131829 & 201806050977. replace & relocate electrical power distribution throughout; (n)pg&e connection. replace all finishes, fixtures & appliances. (e)heating...
- Filed
- Feb 11, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Dec 31, 2024 | Dec 31, 2024 | Approved |
Building inspector Building Inspection · BID-INSP | Dec 31, 2024 | Dec 31, 2024 | Approved |
Electrical inspector Building Inspection · EID-INSP | Dec 31, 2024 | Dec 31, 2024 | Approved |
Code enforcement Building Inspection · CES | Dec 31, 2024 | Dec 31, 2024 | Approved |
Intake Building Inspection · INTAKE | Dec 31, 2024 | Dec 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 31, 2024 | Dec 31, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 31, 2024 | Dec 31, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Jan 22, 2025 | Feb 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2025 | Feb 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 12, 2025 | Feb 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Mar 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2025 | Mar 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 12, 2025 | Feb 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2025 | Feb 27, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 12, 2025 | Oct 6, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2025 | Sep 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2025 | Sep 8, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 12, 2025 | Sep 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2025 | Sep 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 29, 2025 | Sep 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 6, 2025 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $4,281,550
| Name | Role | License on permit |
|---|---|---|
| John Git Hoong Lum John Lum Architecture | Architect | 21837 |
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022