1060 Key Av
San Francisco permit 202412317586 · Bayview Hunters Point
Voluntary seismic upgrade at hope and peace buildings and patch/repair of affected areas. it will also provide accessibility improvements at the main entrance of the hope building.
- Filed
- Jan 21, 2025
- Issued
- Jun 18, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 30, 2024 | Jan 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2025 | Jan 21, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 21, 2025 | Feb 13, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2025 | Feb 19, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 21, 2025 | Jan 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2025 | Jan 30, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 21, 2025 | Jun 4, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2025 | Feb 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 7, 2025 | Mar 17, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 19, 2025 | Mar 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 20, 2025 | Mar 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 3, 2025 | Apr 9, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 2, 2025 | May 28, 2025 | Approved |
Disabled access review Building Inspection · DAD | May 9, 2025 | May 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 28, 2025 | May 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 28, 2025 | May 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 28, 2025 | May 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 30, 2025 | Jun 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 3, 2025 | Jun 4, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $4,260,000
| Name | Role | License on permit |
|---|---|---|
| Peter Wright Pfau Pfau Long Architecture | Architect | C21794 |
| Zack Kardon Murphy Burr Curry Inc. | Engineer | C69106 |
| Christopher James Wood Luke And Associated | Engineer | C72184 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2015