1060 Key Av

San Francisco permit 202412317586 · Bayview Hunters Point

Seismic retrofit or foundationFull plan reviewIssued
Street view · Jun 2015
Google Street View of 1060 Key Av, Jun 2015
Scope of work
As written on the permit application.

Voluntary seismic upgrade at hope and peace buildings and patch/repair of affected areas. it will also provide accessibility improvements at the main entrance of the hope building.

Timeline
Key dates from the city record.
Filed
Jan 21, 2025
Issued
Jun 18, 2025 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
19 stops across 5 departments
Comments issued
6 times, by Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 14, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 21, 2025Administrative

Building plan review

Building Inspection · BLDG

Feb 13, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 19, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 24, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jan 30, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Jun 4, 2025Administrative

Street use and mapping

Public Works · DPW-BSM

Feb 25, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 17, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 19, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 20, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 9, 2025Issued Comments

Building plan review

Building Inspection · BLDG

May 28, 2025Approved

Disabled access review

Building Inspection · DAD

May 28, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

May 29, 2025Approved

Fire prevention review

Fire Department · SFFD

May 29, 2025Approved

Street use and mapping

Public Works · DPW-BSM

May 29, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jun 18, 2025Administrative

Zoning review

Planning · CP-ZOC

Jun 4, 2025Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$4,260,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Peter Wright Pfau

Pfau Long Architecture

ArchitectC21794
Zack Kardon

Murphy Burr Curry Inc.

EngineerC69106
Christopher James Wood

Luke And Associated

EngineerC72184
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202412317586 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record