2230 Jerrold Av
San Francisco permit 202501077901 · Bayview Hunters Point
Construction of an emergency generator to support the meals on wheels, sf production and support center. site work includes structural slab, electrical conduits to and from the building and an emergency generator. the emergency generator will be enclosed by a pre-fabricated enclosure.
- Filed
- Mar 5, 2025
- Issued
- May 14, 2025 (2 months after filing)
- Completed
- Oct 21, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 7, 2025 | Jan 7, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2025 | Mar 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 8, 2025 | Jan 8, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Jan 8, 2025 | Jan 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 8, 2025 | Jan 8, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Jan 8, 2025 | Jan 8, 2025 | Not Applicable |
Zoning review Planning · CP-ZOC | Jan 8, 2025 | Jan 8, 2025 | Not Applicable |
Electrical plan review Building Inspection · MECH-E | Jan 9, 2025 | Jan 9, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jan 9, 2025 | Jan 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2025 | Feb 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2025 | Feb 13, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 13, 2025 | Feb 28, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 6, 2025 | Mar 11, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 6, 2025 | May 1, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Mar 10, 2025 | Apr 9, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 7, 2025 | Apr 9, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 21, 2025 | Apr 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 21, 2025 | Apr 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2025 | Apr 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 21, 2025 | Apr 22, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 21, 2025 | Apr 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 1, 2025 | May 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,400,000
| Name | Role | License on permit |
|---|---|---|
| Carl Milsum A.J. Miller & Associates | Engineer | S6190 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026