20 Santa Marina St
San Francisco permit 202501087939 · Bernal Heights
Demolishing the 2 story rear yard deck, combining the existing 20 santa marina w/ 22 santa marina & creating 1 story studio addition to rear yard to replace (e) 20 santa marina. top flr will be incorporated as part of 22 santa marina & get addition of another bedroom upstaris.
- Filed
- Feb 13, 2025
- Issued
- Sep 3, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 18 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 6, 2025 | Jan 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Feb 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2025 | Feb 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2025 | Mar 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2025 | Mar 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 13, 2025 | Feb 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2025 | Feb 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2025 | Feb 19, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 13, 2025 | Jul 10, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Mar 21, 2025 | Mar 21, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 14, 2025 | May 22, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 14, 2025 | Jun 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2025 | May 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 13, 2025 | Jun 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 18, 2025 | Jun 23, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 18, 2025 | Jun 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2025 | Jun 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2025 | Sep 3, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Grace Harter O'rourke | Payor | C37272 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026