158 Flood Av
San Francisco permit 202501098034 · West of Twin Peaks
Ground fl - add 2 bedrms, add 1 bathrm, media/gym room & laundry @ ground fl; 2nd fl - (e) kitchen to be renovated, relocate interior stairs to other side of house; improve the rear deck increasing 885 sf of conditioned space
- Filed
- Jan 9, 2025
- Issued
- May 8, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 17 stops across 4 departments
- Comments issued
- 3 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 9, 2025 | Jan 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 9, 2025 | Jan 9, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Jan 10, 2025 | Jan 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 10, 2025 | Jan 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 10, 2025 | Jan 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 10, 2025 | Jan 10, 2025 | Approved |
Intake Building Inspection · INTAKE | Feb 26, 2025 | Feb 26, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 26, 2025 | Feb 26, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Feb 28, 2025 | Feb 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 28, 2025 | Feb 28, 2025 | Approved |
Intake Building Inspection · INTAKE | Mar 12, 2025 | Mar 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 12, 2025 | Mar 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 12, 2025 | Mar 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2025 | Mar 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 12, 2025 | Mar 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2025 | Mar 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 8, 2025 | May 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $311,360
| Name | Role | License on permit |
|---|---|---|
| Viet Quoc Truong | Architect | C-37240 |
| Ken Guan Kg Associates | Engineer | C63472 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026